Dan Lipman, head of the company’s Energy Systems division, said the project remains at an early stage, with only site preparation and geological work underway. The pouring of the first nuclear concrete is planned for 2028, but Lipman said that this timeline hinges on signing the EPC contract and ordering long-lead components, such as key reactor parts, without delay.